
Old House Roofing · Blog
What a tear-off uncovers on a pre-1940 house
The shingles are the easy part of reroofing an older home. The real question is what the crew finds once the old roofing is off, because on a house built before 1940 the deck underneath is usually sawn boards, not plywood, and its condition sets the scope. Here is what tends to turn up, what the code asks of it, and how an estimate should price it.
- Attic-side deck check
- Deck work priced line by line
Why prewar roofs sit on boards
Houses built before plywood sheathing came into common use were roofed on sawn boards nailed across the rafters. In our part of the region, that describes a very large share of the housing. In the Census Bureau's American Community Survey (2020 to 2024 five-year estimates), homes built in 1939 or earlier make up about 56.8 percent of housing units in ZIP 19119 (Mt. Airy), 52.0 percent in 19144 (Germantown), 46.7 percent in 19118 (Chestnut Hill), 52.8 percent in 19066 (Merion Station) and 45.2 percent in 19072 (Narberth). Our pre-1940 homes by zip page has the full table for every area we cover.
Most of those houses have been reroofed at least once since they were built, and some three or four times. Each round left something behind on the deck: nails, patches, a layer of felt, sometimes a whole second roof. A tear-off clears all of that away and shows the deck as it really is.
The three decks we usually find
Solid board decking under slate. Slate is heavy and is nailed to a continuous deck, and the current code still requires slate to be fastened to a solidly sheathed roof. When a tired slate roof comes off a Chestnut Hill or Mt. Airy house, the boards under it are often in decent shape, because slate kept them dry for decades. The usual issues are boards split by old slate nails, soft spots under long-running leaks at valleys and chimneys, and gaps where boards have shrunk.
Spaced sheathing from an old wood-shingle roof. Many early houses were first roofed with wood shingles laid on boards with gaps between them, so the shingles could dry from below. The code still allows that for wood shingles: spaced boards at least 1x4 nominal, set on centers equal to the shingle exposure. When asphalt replaced those wood shingles decades ago, the gaps were sometimes left open. Asphalt needs a continuous deck, so spaced sheathing has to be closed in before the new roof goes on.
A patchwork deck. On houses that went from slate or wood to asphalt in the middle of the last century, it is common to find original boards, plywood patches from later leak repairs, and one or two layers of old asphalt that were nailed straight over the first. Each patch is a place where the surface steps up or down a little, and each step shows through new shingles if it is not corrected.
What the code expects of the deck
Pennsylvania's Uniform Construction Code has used the 2021 International Residential Code since January 1, 2026. Philadelphia houses are permitted through the city's Department of Licenses and Inspections, and Cheltenham, Jenkintown, Lower Merion and Narberth each run their own permit offices; our roof rules by municipality page lists them. The deck provisions that come up most on an older house are short:
- Solid deck for asphalt. Section R905.2.1 says asphalt shingles shall be fastened to solidly sheathed decks. Gapped boards do not qualify as-is.
- Nail penetration. Section R905.2.5 requires roofing nails long enough to go at least ¾ inch into the sheathing, or all the way through it where the sheathing is thinner than ¾ inch. Brittle or thin old boards that will not hold a nail are a problem even if they look solid.
- Board thickness. Table R803.1 sets a minimum net thickness of ⅝ inch for lumber roof sheathing over rafters 24 inches apart.
- Tear-off to the deck. Section R908.3 says a roof replacement includes removing the existing layers down to the deck, and Section R908.3.1.1 does not allow a new roof over slate, clay or cement tile, or over two or more existing coverings.
Your permit office may add its own requirements on top of the code, so the deck plan should be settled with the permit, not after it.
Repair the boards, or sheathe over them?
There are two honest ways to make an old board deck ready for asphalt, and the right one depends on what the tear-off shows.
Replace boards where they fail. When most of the deck is tight and sound, the crew cuts out split, rotted or soft boards and puts in new lumber of matching thickness, then fixes loose boards and drives down old nails. This keeps the roof surface at its original height, which matters around chimneys, dormer walls and built-in gutters set to that height.
Sheathe over the whole deck. When gaps are widespread, the boards are brittle, or there are too many patches to make a flat surface, new structural sheathing goes over the old boards across the whole roof. That gives the shingles a continuous nailing surface and evens out the old patches. It also raises the roof surface slightly, so flashing at walls and chimneys, the drip edge and any built-in or half-round gutters have to be detailed for the new height. Our gutters page covers how built-in gutters are handled on older houses.
Plenty of jobs end up as a mix: board repairs on the sound slopes and full sheathing on the worst one.
The attic side of the job
Board decks are noisy and leaky to work on. Hammering on boards transmits through old plaster ceilings, and dust and old roofing granules fall through the gaps into the attic. If you have a walk-up attic with stored belongings, cover them. If there are finished rooms on the third floor with ceilings fastened under the rafters, ask how the crew will protect them, and expect some plaster dust.
The inspection before the job should include the attic wherever it can be reached, because that is where soft boards, old leak stains and daylight through gaps show up. On houses with finished third floors and no attic to walk, the estimate should say plainly that the deck is unseen until tear-off.
How the deck should appear in your estimate
On a pre-1940 house, the deck is the biggest unknown in the price, so the estimate should treat it as a separate line, not a buried allowance:
- A unit price for each replacement board or each sheet of sheathing.
- A statement of whether full sheathing over the boards is included, quoted as an option, or not expected.
- Photos of each area before boards are replaced or sheathing is added.
- How flashing, drip edge and gutters will be adjusted if the roof surface rises.
For published cost figures on prewar jobs, including what moves the total on a slate tear-off, see slate-to-asphalt cost. If your house still has slate in good condition and you are weighing a repair instead, our fix-or-replace guide explains when a slate specialist is the better call. What a full replacement includes from start to finish is on asphalt roof replacement for older homes, and the terms used above are defined in the roof glossary.
Quick answers
Can new asphalt shingles go straight onto the old roof boards?
Why do roofers price deck repairs as a unit instead of a fixed number?
Is spaced sheathing under my roof a sign that something is wrong?
Will the attic get dusty during a tear-off?
Sources
- International Residential Code 2021, Chapter 9 Roof Assemblies, Sections R905.2.1, R905.2.5, R905.6.1, R905.7.1 and R908.3 (Pennsylvania edition on UpCodes), accessed Nov 19, 2026
- International Residential Code 2021, Chapter 8, Section R803.1 and Table R803.1 lumber roof sheathing (UpCodes), accessed Nov 19, 2026
- Pennsylvania Code, Title 34, Section 403.27: the UCC adopts the 2021 International Residential Code as of January 1, 2026 (checked November 19, 2026)
- Census Reporter, ZCTA 19119, ACS 2020-2024 5-year, table B25034 year structure built, accessed Nov 19, 2026
- Census Reporter, ZCTA 19144, ACS 2020-2024 5-year, table B25034 year structure built, accessed Nov 19, 2026
- Census Reporter, ZCTA 19118, ACS 2020-2024 5-year, table B25034 year structure built, accessed Nov 19, 2026
- Census Reporter, ZCTA 19066, ACS 2020-2024 5-year, table B25034 year structure built, accessed Nov 19, 2026
- Census Reporter, ZCTA 19072, ACS 2020-2024 5-year, table B25034 year structure built, accessed Nov 19, 2026
Last checked 2026-10-29.
Rules change. Confirm with the city, township or borough permit office before you rely on any permit or historic-district detail here.
Ask for a free roof inspection
Tell us where the house is, how old the roof is and what it is doing. If you have photos, say so and we will ask for them by email. Outside our core area? Send the form and ask.
We answer form requests Monday to Friday, 9am to 5pm. There is no phone line, so the whole conversation stays in writing.